Monroe Leachate Force Main
After adding a new pump Station, the township of Monroe was in need of over 7,500 Linear feet of 10” Double wall Force main and a leak detection system to ensure that any leaks in the pipe could be found and addressed immediately.
Due to the need to bend around corners and drill under residential neighborhoods, the job was completed in 11 separate drills in lengths ranging from 300, to 1000 Linear feet at a time using our DD-8 Drill.
Once the Drilling was completed, we installed a leak detection system consisting of 13 separate detectors that connected to the pipe as well as two new manholes to allow physical access to the pipe.